FMPA's All-Requirements Project members have ownership interest in 14 operating power plants and one unit currently under construction.
| Resource | Ownership | Megawatts | Fuel Type |
| Cane Island Unit 1 |
50% | 40 | Natural Gas |
| Cane Island Unit 2 |
50% | 120 | Natural Gas |
| Cane Island Unit 3 |
50% | 250 | Natural Gas |
| Cane Island Unit 4 Under Construction |
100% | 300 | Natural Gas |
| Key West Unit 2 |
100% | 14 | Oil |
| Key West Unit 3 |
100% | 14 | Oil |
| Key West Unit 4 |
100% | 44 | Oil |
| Indian River Unit A |
39% |
41 | Natural Gas |
| Indian River Unit B |
39% |
41 | Natural Gas |
| Indian River Unit C |
21% |
112 | Natural Gas |
| Indian River Unit D |
21% |
112 | Natural Gas |
| Stanton Unit 1 |
6.5% |
425 | Coal |
| Stanton Unit 2 |
5.2% |
429 | Coal |
| Stanton Unit A |
3.5% | 656 | Natural Gas |
| Treasure Coast Unit 1 |
100% | 300 | Natural Gas |